PROJECTS

Raymond International
has a long track record of proven results for major corporations.  The following is a selection of successfully completed Recent Pipeline Service Projects.   Alternatively, click here to see a list of our Large Diameter Pipe and Tunnel Lining Projects.


Recent Raymond Pipeline Service Projects

YEAR

PROJECT DETAILS

CLIENT

COUNTRY

LENGTH

DIAMETER

2016-2017

Design, Supply & Fabrication of IGF Skids for EWT Project GC-29 - Cameron-Petrofac- KOC Project

Kuwait Oil Company

Kuwait

Pipe Spools

75-600 MM

2016-2017

New Gathering Centre, GC-30, in North Kuwait. Larsen & Turbo Limited

Kuwait Oil Company / ABJ

Kuwait

Pipe Spools

75-600 MM

2016-2017

UMM Wual Phosphate Plant Tailing Storage Facalities

FMSCO / Saudi Arabian Mining Company

Saudi Arabia

Pipe Spools

50, 80, 250 & 350 MM

2016-2017

New Gathering Centre, GC-31, in North Kuwait. DODSAL

Kuwait Oil Company

Kuwait

Pipe Spools

75 - 600 MM

2016-2017

National Water Company (NWC) / Water Transmission Line to Al-Shareef, Taif

G5

Saudi Arabia

18 KM

1200 & 1600 MM

2016-2017

Water Transmission Line for Jazan Military City Works Project

G5 / Ministry of Defence

Saudi Arabia

18 KM

100 MM

2016-2017

Effluent Water Treatment and Injuction Plant (NK). HDPE LINER Installation to Carbon Steel Pipe

Kuwait Oil Company

Kuwait

248 KM

150-500 MM

2016-2017

RABIGH II PROJECT

GSEC - GS Engineering & Construction Corp.

Saudi Arabia

KM

50 - 1000 MM

2016-2017

Clean Fuels Project Patrofac / Samsung

Kuwait National Petroleum Company

Saudi Arabia

Pipe Spools

100 - 600 MM

2016-2017

Clean Fuels Projects, KNPC - Kharafi National

KNPC / SKEC-JGC JV

Kuwait

16 KM

100-600 MM

2015

WARA - Presure Maintenance Project

Kuwait Oil Company / GSEC

Kuwait

Pipe Spools

100-600 MM

2015-2016

Water Transmission System Pipeline Makkah Ring Main

Ministry of Electricity & Water (MOEW) / Ali Sher

Saudi Arabia

24 KM

1400-2000 MM

2015-2016

Water Transmission System Pipeline Kholas to Rabigh

Ministry of Electricity & Water (MOEW) / Ali Sher

Saudi Arabia

51 KM

1400 MM

2015-2016

Jazan Refinery and Terminal Project (EPC 9

KCC / ARAMCO

Saudi Arabia

Pipe Spools

109,000 inch Dia

2015-2016

Jazan Project

Bemco

Saudi Arabia

93578 inch Dia

1650 & 4000 MM

2015-2016

NWC - Makkah Water Pipeline CN #18C

Al Shakhan

Saudi Arabia

Pipe Spools

1400 & 2000 MM

2015-2016

Hafar Al Batin WTS Pipeline

MAPA

Saudi Arabia

29 KM

1100 MM

2015-2016

SWCC - Khafji Province WTS Newfeeding line pipe supply

G5

Saudi Arabia

11 KM

900 MM

2015-2016

Replacement of Industrial Waste Discharge Line from PS7 to PS9 Jubail

MARAFIQ

Saudi Arabia

LOT

2015-2016

SADAF EOP Project

China Engineering

Saudi Arabia

100 & 500 MM

2015-2016

Midyan Gas Processing Facility (MGPF)

L&T / ARAMCO

Saudi Arabia

31,000 inch dia

2015-2016

Water Transmission line from field wells to north west of Buraidah

Ministry of Electricity & Water (MOEW) G5

Saudi Arabia

81 KM

1000, 1200, & 1500 MM

2015-2016

New Riyadh City Feeder Pipeline

Saline Water Conversion Corporation - SWCC / RTCC

Saudi Arabia

133.5 KM

2000-2500 MM

2014-2015

Longford Gas Conditioning Plant of Exxon Mobil - Australia

Flour-Exonn Mobil

Bahrain

Spools

50-700 MM

2014-2015

Luberef Yanbu Refinery Expansion Project

SAMSUNG

Saudi Arabia

150-1200 MM

2014-2015

Sohar Refinery Improvement Project

Sohar Refinery

Oman

7.5 KM

100-1800 MM

2014-2015

MWE - Main Water Transmission Line from Kholas, Rabigh to Jeddah City

Ministry of Electricity & Water (MOEW)

Saudi Arabia

109 KM

1200 MM

2014-2015

Transmitting of Treated Water from Al Khobar ot Al Hasa

Ministry of Electricity & Water (MOEW)

Saudi Arabia

182 KM

900, 1000, & 2200 MM

2013-2016

Water Transmission System Pipeline To Hail Village

National Water Company (NWC) / Bin Sammar

Saudi Arabia

106.5 KM

900 MM

2013-2014

SWSS from Fujairah to Abu Dhabi - N7396B

ADWEA / TRANSCO

UAE

Pipe & Fittings

100-1200 MM

2013-2014

Construction & Maintenance of WDC-II Mina Ahmadi North Kuwait

Ministry of Electricity and Water (MEW # 39 GSEC)

Kuwait

12.5 KM

150-2200 MM

2013

West Qarna Gas pipe line project - Iraq

FLOUR - Exxon Mobile

UAE

Pipe Bends

150-500 MM

2013

Seawater intake and return pipeline for off sites project

Borouge Petrochemical Complex

UAE

2 KM

100-2700 MM

2013-2014

MWE - Main Water Transmission Line from Hili, Yuba, Al Laith Dams to Al-Shoaiba Plant (Phase - 1 & 3)

Ministry of Electricity & Water (MOEW)

Saudi Arabia

115 KM

1400 MM

2013-2014

MWE - Water Transmission Line from Hili, Yuba, Lith Dams to Shoaiba Plant, Phase-2

Ministry of Electricity & Water (MOEW)

Saudi Arabia

176 KM

500, 1400, 1500 MM

2013-2014

Habshan-Maqta-Taweela Gas Pipeline Project

GASCO / DODSAL

UAE

Pipe & Fittings

400-1300 MM

2012

Fire Water Pipeline at MOT Fujairah

IPIC / ADCOP

UAE

3 KM

700 MM

2012-2013

SWCC - Ras Al khair - Hafr Al Batin WTS Project

Saline Water Conversion Corporation - SWCC

Saudi Arabia

402 KM

75 - 1100 MM

2012-2013

SAAD (WASIYA) Pipeline

National Water Company

Saudi Arabia

128 KM

1600 MM

2012-2013

Yambu to Madina Water Transmission System Phase 3.

Saline Water Conversion Corporation - SWCC

Saudi Arabia

421 KM

700 - 1900 MM

2012-2013

Liwa Strategic Water Storage Project

Abu Dhabi Water & Electricity Authority (ADWEA) and TRANSCO

UAE

155 KM

150 - 1200 MM

2012-2013

Transmitting of Treated Water from Al Khobar ot Al Hassa

Authority Al Hassa, Ministry of Agriculture

Saudi Arabia

17 KM

900 - 1000 MM

2012-2013

SWCC – Ras Alkhair to Riyadh Water Transmission System Pipeline Project.
Saline Water Conversion Corporation - SWCC

Saudi Arabia

910 KM

1900 MM

2012-2013

SWCC – Ras Alkhair to Riyadh Water Transmission System Pipeline Project

Saline Water Conversion Corporation - SWCC

Saudi Arabia

910 KM

1900 MM

2012-2015

SWCC - Yanbu - Madina Water Transmission System Pipeline Project

Saline Water Conversion Corporation - SWCC

Saudi Arabia

608 KM

300-1900 MM

2012-2015

NWC - Strategic Plan for Riyadh WTS, Contract No. 3a, 11, 15 & 16

National Water Company (NWC)

Saudi Arabia

24 KM

1400-2400 MM

2012-2013

MEW #37 / Construction and Maintenance of 3x1600MM Dia. Fresh Water Pipeline from Mina Abdullah WDC II to West Funaitees.

Ministry of Electricity of Water

Kuwait

90 KM of Field & CML Joints

1600 MM

2012

Natural Gas Pipe Line to Hidd - SULB Project

BAPCO

Bahrain

1.6 KM

500 MM

2012

NWC - Strategic Plan for Riyadh WTS, Contract No. 13

National Water Company (NWC)

Saudi Arabia

16 KM

1600, 2000 & 2200 MM

2011-2012

Shah Gas Project in Abu Dhabi

ADGAS / SAMSUNG

UAE

6.5 KM

50-450 MM

2011-2012

MEW #58 / Mina Abdullah WDC II Pumping Station

Ministry of Electricity and Water

Kuwait

6 KM

72-2400 MM

2011

Seawater Process Pipelines at Power & Desalination Plant

Bahrain Petroleum Company

Bahrain

5 KM

100-1200 MM

2011-2014

Azzour & Subiya Water Transmission Projects

Ministry of Water & Electricity (Kuwait)

Kuwait

280 KM

1200 MM

2011-2012

KOC - North Kuwait New Booster Station BS-132 & Enhancement to BS-131

Kuwait Oil Company

Kuwait

Plants Pipings

75-600 MM

2011-2015

SWCC - Al Taif- Al Baha Water Transmission System Line Project

Saline Water Conversion Corporation - SWCC

Saudi Arabia

215 KM

1000 MM

2010-2011

Twin DN 1600 CS Pipeline from Tap - 12 to Al Ain Reception Center

ADWEA / TRANSCO

UAE

55 KM

200-1600 MM

2010-2011

Replacement of Steam Turbo - Generators at No. 2 Power Plant

BAPCO

Bahrain

5 KM

200-1200 MM

2010-2014

SWCC - Ras Al khair - Hafr Al Batin WTS Project.

Saline Water Conversion Corporation - SWCC

Saudi Arabia

380 KM

1100 MM

2010

KOC - Upgrading / Modification to Tankage, Injection Pump Seal, Water & Drainage System at MWIP

Kuwait Oil Company

Kuwait

Plant Pipings

75-600 MM

2009-2011

Fujairah to Al-Ain Water Transmission System Phase 2 (N5805)

Abu Dhabi Water & Electricity Authority (ADWEA) and TRANSCO

UAE

130 KM

1600 MM

2009-2010

Great Man Made River Project Ghadames-Zwara-Az Zawiyah Water System

Great Man Made River Authority

Libya

23 KM

1200 MM

2009-2010

KOC Project New GC-24 / Process Piping

Kuwait Oil Company

Kuwait

Plant Pipings

75 - 750 MM

2008-2010

ADGAS Offshore Gas Development - Various Pipelines Projects

Abu Dhabi Gas Company

UAE

30 KM

250 - 3100 MM

2008-2009

N-2622.1 Pipeline at Abu Dhabi Island and Adjacent Areas - Lot A, B, & C

ADWEA / TRANSCO

UAE

2 KM

400 - 1600 MM

2008

KPPC Aromatics Offplot Works - Seawater Fire Fighting Pipelines

Kuwait National Petroleum Company

Kuwait

5 KM

100 - 150 - 200 - 400 & 500 MM

2006

KNPC New Ethane Recovery Plant - Process Water Pipelines

Kuwait National Petroleum Company

Kuwait

5 KM

100 - 1200 & 1800 MM

2006

KNPC Expansion of New Oil Pier (Berth 5 & 6) Fire Water Pipelines

Kuwait National Petroleum Company

Kuwait

10 KM

700 MM

2005

Qatif Flank Lines - Operation Producing Department Seawater and Brackish Water Pipelines

Saudi Aramco

Saudi Arabia

80 KM

100 - 600 MM

2003 - 2005

Qatif Flank Lines - Operation Producing Department Seawater and Brackish Water Pipelines

Saudi Aramco

Saudi Arabia

72 KM

100 - 1050 MM

2000 - 2002

Fujairah to Al-Ain Water Transmission System Phase 1

Abu Dhabi Water & Electricity Authority (ADWEA)

UAE

380 KM

1600 MM

2000

UWIPS-4 to UWIPS-5 Seawater Transfer Pipeline

Saudi Aramco

Saudi Arabia

24 KM

1050 MM